Biogas Plants

Project

 

Description

Year of finish

BS Vysoká Repair of fermentor equipment2018
BS Vyškov Reconstruction of biofilter and postfermentor2017
BWWTP Rybitví - Pardubice II. phase, waste receiving, separation and hygienization2016
BWWTP Rybitví - Pardubice Biogas station reconstruction2013
Humpolec Cogeneration at WWTP2012
Plzeň Generation and cogeneration at WWTP

2012

Ladzany

 více informacíPD and implementation of a 1000 kW vegetable substrate biogas plant

2010

Hontianské Moravce

 více informacíPD and implementation of a 1000 kW vegetable substrate biogas plant

2010

Strážovice

 více informacíPD and implementation of a 500 kW vegetable substrate biogas plant – general supplier

2010

Louny Biogas generation and cogeneration at WWTP

2010

Senica Biogas generation and cogeneration at WWTP

2010

Třeboň Reconstruction of a pig manure biogas plant

2009

Hurbanovo Extension of an agricultural biogas plant from 270 to 600 kW

2009

Varnsdorf

 Biogas generation and cogeneration at WWTP

2008

Šala

 Biogas generation and cogeneration at WWTP

2008

Povážská Bystrica Biogas generation and cogeneration at WWTP

2008

Bratislava –Vrakuňa

 Biogas generation and cogeneration at WWTP

2007

Vysoká více informacíBiogas generation and cogeneration at WWTP

2007

Hurbanovo PD and implementation of a 270 kW corn silage biogas plant - 270 kW

2005

Pelhřimov Biogas generation and cogeneration at WWTP

2002

Benešov

 Biogas generation and cogeneration at WWTP

2001